Plagued by Supply-Chain Issues, Pro-Audio Suppliers Invest and Upgrade Wheatstone doubles down on manufacturing, inventory; Calrec targets infrastructure By Dan Daley, Audio Editor Tuesday, August 3, 2021 - 10:47 am
Print This Story | Subscribe
Story Highlights
Supply-chain problems have beset global manufacturing for over a year, since the COVID pandemic closed down much of the world's manufacturing and transport. The situation has been exacerbated by growing demand as the pandemic recedes in some areas, even as the supply chain, materials, and especially the critical microchip-supply ecosystem have barely begun to reopen and re-establish themselves. Professional audio has not been immune to any of this and has been scrambling to respond.
Lead times on everything, including fairly standard parts like diodes and capacitors, are all over the map, says Wheatstone Production Manager Matt Wilson, citing a 61-week lead time on capacitors, for example. Metal extrusions have a normal six- to eight-week lead time, [which] went to 13 weeks. It then climbed to a 24-week lead time. Wheatstone has been fortunate in that we have reserves of the [necessary] ADC chip, along with other components, and, earlier this year, we were able to buy up even more in bulk.
In broadcast, the audio-console sector in particular has been vulnerable to supply-chain issues and other disruptions to manufacturing, especially the chip shortage.
It has certainly been a challenge, and still is, but we have done a lot of work to mitigate supply issues, and being part of Audiotonix gives us better buying power and puts in a stronger position than if we were on our own, explains Kevin Emmott, marketing manager, Calrec, one of four console brands under the aegis of Audiotonix. We also took the opportunity to undergo changes to our infrastructure in the last 12 months and made significant investments at the factory during the pandemic, concentrating on our R&D and in-house production facilities so we were able to come out stronger.
Some Context on Chips The microchip landscape was fragile to begin with. Only a handful of suppliers were making ADC/DAC chips, which are used in phones, cameras, anything and everything that converts analog audio to digital and vice versa. But only a few - notably, Cirrus Logic and AKM - make the kind and quality of ADC/DAC parts used in pro, musical-instrument, and broadcast products. AKM experienced a massive factory fire in October and hasn't yet ramped up production of those chips.
Another complication is that chips from different manufacturers are not necessarily interchangeable. For instance, pin configurations for AKM's ADC chips are different from those of Cirrus Technology's equivalent ADC/DAC chips; AKM chip users would have to redesign their circuit boards to accommodate a different chip-pin configuration.
Industry sources indicate that chip-supply disruptions won't be resolved anytime soon and will likely continue to fuel price increases for products ranging from audio consoles to automobiles.
Wheatstone's Million-Dollar Investment
One aspect of Wheatstone's response to the current environment is a literal doubling down on its domestic manufacturing capacity, with a million-dollar investment in large component buys and new equipment at its manufacturing facility in New Bern, NC. The goal, according to an announcement made in mid July, is to increase production 100% at the factory, where all products from Wheatstone and corporate sibling Audioarts Engineering are made - from machining, fabrication, screening and circuit-board surface mounting to final testing and AoIP-system configuration.
Manufacturing in-house lets us respond more quickly to changes and gives us much better control over a volatile supply chain, says Wilson. By maintaining high inventories on components and investing in additional machinery, we are more than able to meet our customer requirements well into and past 2022.
Among the new additions to its 52,000-sq.-ft. factory floor are a second multi-axis CNC milling machine and a larger-format brake press to keep up with the production demand for precision metal work. An additional surface-mount machine also will be added, to increase the production quantity and quality of the circuit boards used in Wheatstone consoles, Blade interfaces, and other audio processors.
The ramp-up in manufacturing capacity comes ahead of a multimillion-dollar contract to provide WheatNet-IP audio-console surfaces, network devices, and system preconfiguration for 247 studios in 32 U.S. markets, for an undisclosed broadcast and production customer, with the majority of completed systems to ship through September.
Calrec Aims for More-Flexible Manufacturing According to Calrec Operations Manager Helen Jones, that company used time during the pandemic to upgrade some infrastructures and develop some key areas.
Calrec's Helen Jones: World events are a challenge to our supply chains. We are still dealing with the effects of COVID-19, and, in the UK, we've also had to plan for Brexit.
First, we completely refurbished our R&D office space to help our 50 engineers work in a way that reflects whatever stage the project is at, whether that's collaboratively where engineers can brainstorm and be more creative or in quiet, focused office space, she explains. We took the opportunity to also install more energy-efficient solutions and better insulation. We are already using renewables for our electric provision, and, by 2022, we have a target to be carbon-neutral on gas.
We also redesigned and upgraded our production facility at Nutclough Mill [in Hebden Bridge, West Yorkshire, UK], Jones continues, to create a more flexible manufacturing process that can adapt to the changing needs of our customers. All parts of the process